Getting Even Better: Bypass-Taxiway Construction Schedule – New Closure Date
Updated on June 26, 2025, at 11:40 a.m.
NOTAMs will be issued and this page will be updated as soon as any new information is available. As updates are made on this page, those changes will be noted in red.
Raleigh Exec is enhancing jetport operations with a new bypass-taxiway, and the second phase of construction is now underway. Check below for the latest construction schedule and any potential disruptions, which will be updated as needed.
Runway 3 and 21 has been displaced — beginning on April 28, 2025 — from the existing 6,500 feet to a temporary length of 5,514 feet. The runway is expected to be operational to its full length and be reopened on June 28, 2025, at 7:00 a.m., though the actual reopening date depends on weather conditions during construction.
Runway 3 and 21 will close overnight on Sunday, June 29, 2025, at 8:00 p.m. (EDT) until Monday, June 30, 2025, at 7:00 a.m. (EDT) to remove the displacement and will reopen to its full length that morning.
We appreciate your understanding as we complete this new bypass-taxiway that will significantly enhance operations and make your experience even better here at Raleigh Exec.